Rep. Mike Levin held a press conference at the San Onofre Nuclear Generating Station to discuss the facility's ongoing decommissioning process and the current state of the coastal site. During the event, Rep. Mike Levin highlighted a report that outlines significant progress made since the task force formation in two thousand nineteen. The report details the massive scope of the project, which has been underway for several years at the location.

According to the details provided by Rep. Mike Levin, fifty-two of sixty-two plant structures have already been demolished as part of the massive cleanup effort. Furthermore, over seven hundred million pounds of material have been successfully removed from the site. The facility's twin domes, which were originally built in nineteen eighty-three and nineteen eighty-four, are expected to be completely dismantled by the end of two thousand twenty-seven.

Looking further ahead in the timeline, major decommissioning work across the entire site is currently on track for completion by the end of two thousand twenty-eight. Despite these substantial physical reductions to the plant's footprint, Rep. Mike Levin pointed out that more than sixteen hundred tons of spent fuel remain near the Pacific Ocean.

To help combat these ongoing challenges, Rep. Mike Levin noted that nearly two hundred fifty million dollars has been secured for nuclear waste management initiatives. Reflecting on the journey since the task force's inception, Rep. Mike Levin offered remarks regarding the broader federal and local efforts. "When I convened the SONGS Task Force in 2019, there was no clear path to move nuclear waste off our coastline. Today, we can point to real progress at San Onofre and growing momentum at the federal level," Rep. Mike Levin told New York Post.

In addition to the decommissioning milestones at the coastal facility, regional updates were also noted during the briefing. In July, governors of five states signed memoranda regarding innovation campuses, signaling broader regional coordination on related technological and infrastructure initiatives.

Even with the closure of the plant and the removal of dozens of structures, Rep. Mike Levin stressed that the ultimate goal of clearing the radioactive material from the region has not yet been fully achieved. Concluding the press conference, Rep. Mike Levin issued a cautious forward-looking statement to attendees and reporters regarding the road ahead. "We cannot mistake progress for a permanent solution. I will keep working across party lines to secure the funding, reforms, and safe storage and disposal options needed to finally get this waste off our coast," Rep. Mike Levin told New York Post.